Project Overview

We upgraded the electrical infrastructure of a commercial facility to support increased capacity and modern equipment loads.

We upgraded the electrical infrastructure of a commercial facility to support increased capacity and modern equipment loads.

The project included a full panel upgrade, three-phase power distribution, and updated wiring across every workspace in the facility.

The project included a full panel upgrade, three-phase power distribution, and updated wiring across every workspace in the facility.

This project focused on bringing an aging commercial facility up to modern capacity and code requirements. Our electricians upgraded the main distribution panel, installed three-phase circuits for heavy equipment, and rewired every workspace with minimal disruption to daily operations.

Electrician in an orange hard hat working on an open electrical panel from a step ladder
Electrician wearing a white hard hat with a headlamp inspecting an illuminated electrical panel at night

Project Challenge

The facility's aging electrical infrastructure could not support new equipment loads, and outdated panels were creating capacity and safety concerns across multiple workspaces.

Electrician holding a bundle of stripped wire ends in front of an electrical panel

Our Solution

We upgraded the main distribution panel, installed dedicated three-phase circuits for heavy machinery, and rewired affected workspaces in coordinated phases to keep the facility operational throughout the project.

Services Included

Main Panel Upgrade

Three-Phase Power Distribution

Workspace Rewiring

Load Capacity Assessment

Emergency Lighting Circuits

Equipment Circuit Installation

Compliance Documentation Review

Electrical Safety Inspection

Final Performance Testing

Project Highlights

Upgraded Main Distribution

Replaced the aging main panel with a higher-capacity distribution system for the whole facility.

Three-Phase Power

Installed dedicated three-phase circuits to safely power heavy commercial equipment.

Phased Rewiring

Rewired each workspace in coordinated phases to avoid disrupting daily operations.

Code-Compliant Capacity

Brought the entire facility up to current code requirements with room for future growth.

Electrical substation with transmission towers and switchgear behind a security fence
Close-up profile of an electrician wearing a white hard hat and yellow safety glasses beside coiled cables
Portrait of a man in a black turtleneck against a dark background
Daniel Whitfield

Facility Manager

Electrio managed a complex upgrade across our entire facility without shutting us down for a single day. The new system has completely eliminated our capacity issues.

NEWSLETTER SUBSCRIPTION

Stay connected with expert electrical tips

No spam. Unsubscribe anytime.

Create a free website with Framer, the website builder loved by startups, designers and agencies.